budget – Zistemo Knowledge Base https://zistemo.com/knowledge-base Zistemo is the smartest app for instant time and expense tracking. Boost productivity and save time with zistemo. Fri, 19 Oct 2018 18:05:42 +0000 en-US hourly 1 https://wordpress.org/?v=6.0.2 Personal Days on a Project Dashboard https://zistemo.com/knowledge-base/content/personal-days-project-dashboard/ Mon, 12 Mar 2018 11:41:10 +0000 https://moneypenny.me/knowledge-base/?post_type=ht_kb&p=3846 If you set an hours budget for your project (Total Project Hours, Hours per Staff, Hours per Task – more about Project Budget here), you can easily track how much time is spent on this Project.
You can see this information on the Project Dashboard:

– Budget

Shows the number of hours you have set as a budget on the Edit Project page:



– Total Hours

Displays how many hours are spent by all project members.

– Person Days

Time spent on this Project in Person Days:
Person Days = Total Hours/Person Day (hours)
For example:
Personal Days=9 hours/8 hours = 1.13 days


– Remaining Hours

Budget minus Total Hours (spent hours) = 50 – 9 = 41 hours

– Remaining Days

Remaining Hours/Person Day(hours) = 41/8 = 5.13 days.

How can I set hours in one Person Day

You can set how many hours should one Person Day have for your business by entering the number yourself in Settings -> Preferences, as shown below:

]]>